ANCILLARY & INDUCED ACTIVITIES AND INDIRECT & CUMULATIVE

ANCILLARY & INDUCED ACTIVITIES AND INDIRECT & CUMULATIVE

ANCILLARY & INDUCED ACTIVITIES AND INDIRECT & CUMULATIVE IMPACTS SAFEGUARDS TRAINING WORKSHOP ESRA ARIKAN, AGI KISS MAY 2013 DEFINITIONS Ancillary/Linked Activities : Supporting investments needed for project to meet its objectives, although not financed under the project (would not be done in absence of the project) -- e.g. Transmission lines, pipes, roads, borrow pits, etc. include some photos) Induced Activities: Take place because the project is implemented, (usually) not part of project objective but predictable result e.g. Informal settlement along a new road; overgrazing around watering holes, etc. Indirect Impacts: Impacts arising from Induced Activities Cumulative Impacts: overlapping (additive or synergistic) impacts of the project and other projects in the same area, which utilize or affect the same environmental or social

systems References in WB Operational Policies OP 4.01 Annex A (Definitions): Project area of influence: The area likely to be affected by the project, including all its ancillary aspects, such as power transmission corridors, pipelines, canals, tunnels, relocation and access roads, borrow and disposal areas, and construction camps, as well as unplanned developments induced by the project (e.g., spontaneous settlement, logging, or shifting agriculture along access roads). OP 4.01 Annex B (Contents of EIA Report): [EIA] Concisely describes the proposed project and its geographic, ecological, social, and temporal context, including any offsite investments that may be required (e.g., dedicated pipelines, access roads, power plants, water supply, housing, and raw material and product storage facilities). EA Sourcebook #2 (EA Screening): One of the requirements of a full EA is that other current and proposed development activities within the project area and more spontaneous activities spurred by a project (such as migration of people into an area opened up by a road project) must be taken into account. Such cumulative or induced impact may sometimes be the primary determinant of the appropriate level of EA. OP 4.12 policy applies to all components of the project that result in involuntary resettlement, regardless of the source of financing. It also applies to other activities resulting in involuntary resettlement, that in the judgment of the Bank, are (a) directly and

significantly related to the Bank-assisted project, (b) necessary to achieve its objectives as set forth in the project documents; and (c) carried out, or planned to be carried out, contemporaneously with the project. [NOTE: judgement in definition of contemporaneous] IFC Performance Standard 1: Associated facilities are those activities or facilities that: a) are not funded as part of the project; and (b) would not have been constructed or expanded if the project did not exist and without which the project would not be viable Examples of Project Area of Influence) (OP 4.01, Annex A) the watershed within which the project is located; any affected estuary and coastal zone; off-site areas required for resettlement or compensatory tracts; the airshed (e.g., where airborne pollution such as smoke or dust may

enter or leave the area of influence; migratory routes of humans, wildlife, or fish, particularly where they relate to public health, economic activities, or environmental conservation; areas used for livelihood activities (hunting, fishing, grazing, gathering, agriculture, etc.) Areas used for religious or ceremonial purposes of a customary nature. Thermal Power Plant Project and its Ancillary Aspects Quarry& disposal site Coal handling facility Road Do m ina

n tw ind New sub-station Ash storage Power plant field Agricultural facility Road Workers camp Neighborho Resettlement site od Village Landfill for

ash disposal Case Study Road Network Interchange 2 A Interchange 1 B Feeder road C Bank-assisted project is to improve the regional transport system, 3 components: (a) Civil works from B

to C; (b) 2 interchanges; (c) feeder roads to interchanges WB will finance 40% of civil works from B to C; EBRD will finance 40% of interchanges; client will finance the rest EBRD will also finance 100% of a road from A to B, which is essential for achieving the objectives of WB assisted project WB safeguard policies apply to all components of WB assisted project, and all their ancillary facilities, regardless of source of financing; Road from A to B is a linked project

(related activity) Project Example Ancillary Investments (Inspection Panel case) Ghana-Nigeria: West African Gas Pipeline Project (P082502) 2006 (IDA and MIGA Guarantees) Project Development Objective: (a) to improve the competitiveness of the energy sectors of Ghana, Benin, and Togo by promoting the use of cheaper and environmentally cleaner gas from Nigeria in lieu of liquid fuels for power generation and other industrial and commercial uses; and (b) to foster regional economic and political integration that would support economic growth. Project financed: (a)a new pipeline system (678 km long) to transport natural gas from Nigeria to Ghana, Togo, and Benin; (b)spurs to provide gas to power generating units in Ghana, Benin, and Togo; (c)conversion of existing power generating units to gas; and (d) as needed additional compression investments

Environmental Safeguards Instruments prepared: Regional EIA, country-specific EIAs Inspection Panel Case Requesters claims: (1) Requesters from Nigerias Delta Region were concerned with the Projects impact on gas flaring reduction and with the safety of an existing pipeline (Escravos-Lagos Pipeline System in Nigeria) to which the Project was to be linked. E-L Pipeline = pre-existing Ancillary investment Specific complaints included: EIA for WAGP should have included effects of the Project on the existing pipeline (E-L pipeline unsafe due to history of poor maintenance and accidents) low compensation rates for the land they had to give up for the E-L pipeline; in area where the E-L pipeline goes under the sea the construction process hurt their fishing enterprise. (2) In addition: Requesters from Nigeria and Ghana claimed direct issues with the proposed project including inadequate consultation regarding the Projects economic viability, the pipelines safety and the adequacy of proposed emergency response measures, and its impacts on coastal fisheries, inadequacy of compensation for land acquisition, etc. Conclusions of Inspection Panel

Investigation Management and Task Teams position- -EA did not include ELPS because it was not part of the Projects area of influence * : The existing pipeline has been in operation since the early 1990s. It would not be subject to any changes as a result of the implementation of WAGP. ELPS pipeline has substantial customers other than WAGP and thus ELPS pipeline does not depend on WAGP for its continued operation. Panel findings Project should be viewed in broader context of Nigerias and the regions hydrocarbon economy and its social and environmental dimensions: OP 4.01 states the EIA should include the area likely to be affected by the project, including all its ancillary aspects, such as power transmission corridors, pipelines, While WAGP is not responsible for the operation of ELPS pipeline, operation of the ELPS pipeline is essential for gas to flow through the WAGP. Thus ELPS is integral to the success of the WAGP initiative. The project could induce environmental and socioeconomic secondary impacts both upstream and downstream of the Project e.g. industry may increase oil and gas development (drilling new wells) in order to supply additional natural gas through WAGP. This could lead to expansion of ELPS capacity/infrastructure . Therefore, gas supply system upstream of WAGP is within Projects Area of Influence within the meaning of OP 4.01. The Regional EIA properly flags these (upstream gas supply issues, but no analysis of their nature and scope had yet been carried out. An Environmental Audit of ELPS should be carried out

Despite not being disclosed, Integrity Study led to safety inspection of ELPS pipeline and detection/correction of some problems, i.e. To an improvement in its safety *(Nevertheless, Project preparation included an integrity study to evaluate safety of existing upstream & downstream structures including the ELPS pipeline and concluded it was safe). Integrity study was not included in EIA and not disclosed. Application of OP 4.01 vs. Due Diligence Ancillary, Induced and Linked Activities should be identified and addressed in EIA. OP 4.12: explicitly applies to all, including contemporaneous linked activities OP 4.01: explicitly applies only to ancillary activities which are considered part of the project Evolved practice: Ancillary activities: If carried out specifically to serve the project, are treated as part of the project -- WB policies apply directly (e.g. ETLs serving WB-financed power facilities should comply with OP 4.04, even if not financed by WB) If already in place and/or not specifically built to serve the project carry out due diligence audit to determine whether there are any serious environmental or social issues (e.g.: operating without required environmental licenses, pending legal actions, evidence of unaddressed serious negative impacts, etc.) Induced activities: depending on predictability/severity, address through EMP (may involve

actions/agreements beyond the scope of the project). Linked activities: By definition, important for project objectives but not part of project for which WB is providing financing carry out due diligence and work with Borrower/Financers to address any issues identified. If any Ancillary, Induced or Linked activities have impacts that are highly likely and serious and no agreement is reached to resolve them, WB may decide not to finance the project in question (reputational risk) CUMULATIVE EIA IN INTERNATIONAL STANDARDS EU Directives EIA Directive (85/337/EEC) (97/11/EC) (2003/33/EC) (2009/31/EC) (2011/92/EU) Strategic EIA Directive (2001/42/EC) Water Framework Directive (2000/60/EC) and Habitats Directive (92/43/EEC) World Bank Safeguard Policies OP 4.01 OP 4.01 Annex A - Definitions OP 4.01 Annex B Category A Table of Contents of an

EIA OP 4.01 Annex C EMP IFC Performance Standards and Guidance Notes (2012) PS 1 Environmental and Social Risk and Impact Assessment What is Cumulative Impact Assessment? Project A zone of impact Project A site Zone of Impact of directly linked or induced development Facility B zone of impact Important Cultural

Asset - VEC Zone of impact of planned/reasonably foreseeable development or trend Important Env. Asset - VEC Existin g Facility B site VEC EXAMPLES ENVIRONMENTAL ISSUE VEC AIR

Closest settlement Flora/Fauna WATER QUALITY and QUANTITY Other water users such as fish farm owner, farmers ECOLOGY Aquatic species, .. EIA and CEIA EIA should identify potential cumulative impact issues and associated risks: Minor risk Few other significant impact sources Easily

understood impacts and interactions Cumulative impacts section of EIA prepared without in-depth CEIA exercise Major risk Numerous other significant impact sources Complex impacts and interactions In-depth CEIA exercise needed (should be simultaneous and interactive with rest of EIA)

Discussion of Cumulative Impacts within EIA VECs may be general and LACs may be presented in qualitative terms In-depth Cumulative Impact Assessment VECs should be specific and LACs mostly expressed in quantitative terms Usually rely on existing data Often requires collection of additional baseline and impact-related data Usually use relatively simple

analytical tools (e.g. impact matrix) Use more sophisticated and quantitative analytical tools (mathematical or computer modeling of alternative scenarios, dose/response curves, GIS/land use mapping, etc.) Projects to be Considered under Cumulative Assessment Afin B Santral Afin A Santral Operation Kartalkaya Ayval Menzelet Sr

Under constructi on; Adatepe Klavuzlu Dadelen Kandil Sargzel Planned HEPP Hacnno Existing Karakuz Other Kavaktepe luAfin A Plant Hasanali Afin B Plant Gksu Dogutlu Irrigation Geben Ksk Other Planned Afin C, D, ve

E Plants Why Do Because a CEIA? proposed project is likely to have significant impacts on regional Valued Ecosystem Components which are also impacted by other actions/trends (sources) Because the impacts from different sources (stressors) can interact in additive or synergistic ways, not always easy or straightforward to predict, requiring in-depth analysis Because impacts from other stressors can undermine the projects objectives and/or result in unexpectedly severe impacts Because looking at the broader picture might reveal new opportunities for better overall outcomes Because the most feasible and cost-effective mitigation measures might not lie within the context of the proposed project

When to do CEIA? What information is needed to determine whether EIA for Project A needs to take Facility B into account? Starting point: impacts Project A has potential off-site (e.g. air or water emissions, erosion/sedimentation, noise, etc.) which cannot be eliminated through realistic mitigation measures Distance between A and B . are there circumstances where this information might be enough? Located within same ecological system (river/lake basin, watershed, airshed, wildlife home range) what information is needed to know this? what sources can provide it?

Overlapping zones of impact impact on the same VECs . what information is needed to know this? what sources can provide it? .. How to do CEIA: Assessment Framework (Red text indicates how CEIA differs from EIA) 1. Scoping: Identify issues/assets of concern, at a regional scale (information sources: spatial plans, experts, public consultation) Select appropriate Valued Ecosystem Components and determine

Limits of Acceptable Change for those VECs Identify spatial and temporal boundaries for the study based on VECs Identify other stressors (existing and expected future actions and trends) that may affect the same VECs Identify potential impacts of project and of other stressors together they make up the cumulative impacts 2. Data Collection and Analysis: Collect baseline data relevant to VECs and potential impacts -literature, consultation, data collection Assess likely effects of the project on VECs Assess likely effects of other stressors on VECs Evaluate potential cumulative (additive, synergistic) effects to assess total impact; use scenarios and modeling as appropriate 3. Potential mitigation measures: Identify potential mitigation measures for proposed project and where possible, measures to reduce impacts of other stressors Evaluate feasibility and costs, develop realistic mitigation plan -including costs and institutional responsibilities (some of which may be outside scope of the project)

4. Evaluate residual impacts: Compare to pre-determined Limits of Acceptable Change/ objectives/thresholds 5. Follow-up (multi-stakeholder) Monitoring of VECs and mitigation measures (project and other stressors) Adaptive management process to make changes based on monitoring THANK YOU

Recently Viewed Presentations

  • God's Mercy

    God's Mercy

    "God's mercy is his tenderhearted, loving compassion for his people. It is his tenderness of heart toward the needy. If grace contemplates humans as sinful, guilty, and condemned, mercy sees them as miserable and needy." - Millard Erickson2
  • Florida Energy Workforce Consortium

    Florida Energy Workforce Consortium

    Instructor would get login and would then provide logins to students Valerie Taylor will be coordinator so if we want to offer this way, need to coordinate through Valerie NOTE: Have to send in EIF Approved Provider application months in...
  • Definition? - Rice University

    Definition? - Rice University

    Students learn best through personal exploration and active thinking. By answering students' questions, we rob students of the opportunity to develop good thinking habits. Guide by asking probing or scaffolding questions, by making suggestions, by waiting. Language is critical in...
  • CSC 458/2209  Computer Networks Handout # 4: Link

    CSC 458/2209 Computer Networks Handout # 4: Link

    Announcements. Programming assignment 1 out (Sep 17th). To be completed in groups of . 2-3. people. Due: Oct. 11th at 5PM. Will have test runs during the last week.
  • Innovative Rubrics for Online Discussions

    Innovative Rubrics for Online Discussions

    What is the purpose of a rubric? Meant to communicate expectations. Provides consistent criteria for grading. Provides feedback to student. A scoring guide used to evaluate. elevate. the quality of student posts via modeling desired behavior.
  • ODOTs Structure Management System (SMS) Mike Brokaw, P.E.

    ODOTs Structure Management System (SMS) Mike Brokaw, P.E.

    BMS Data? Offline Version? Step 1: Get a Username and Password to enter SMS. ODOT Employees. You already have one, the Username and Password will be the same as your login for your ODOT computer (skip Step 2)
  • Claim- Evidence- Reasoning (C.E.R.)

    Claim- Evidence- Reasoning (C.E.R.)

    Reasoning. Reasoning is the explanation that connects your claim to the evidence that supports it or why you think your claim (answer to the question) is correct .. It shows . why. the data you chose counts as evidence. It...
  • Peri-operative anticoagulation

    Peri-operative anticoagulation

    Complementary therapies. Matthew A Bartlett, M.B., B.Ch., BAO. Assistant Professor of Medicine. General Internal Medicine. Department of Internal Medicine